Onshore construction

Works along the onshore cable route, at the Brooklands construction compound and on the new substation were divided into 12 stages for ease of reference during construction.

Public Rights of Way

As part of our construction planning, we consulted with users of the Public Rights of Way (PRoW) tracks along the cable route, to ensure that works requiring closures be communicated in a clear and helpful way. During the construction works we have crossed 32 Public Rights of Way and for each of these looked to minimise closures, and provide suitable temporary diversions where necessary.

Due to the flexibility in the construction programme, we have not been able to give specific dates of closures significantly in advance of construction. However, signage has been posted on the routes 14 days before any anticipated closures due to works, and more detailed information posted 5 days before the closure.

The table below will be updated with advanced warning of any PRoW closures as well as information about the planned works and construction activity progress.

These two diagrams below show examples of how a closed and an open Public Right of Way would be configured.

Closed PROW illustration example

Open PROW illustration example

View map of stages

Stages

Stage 1 - Bolney Substation

View map of stage

Public Rights of Way
Reference
Update
1T
Long term temporary closure (2 years). Local diversion in place.
Footpath 8T
Long term temporary closure (2 years). Local diversion in place.

Stage 2 - Bob Lane and Herring Stream

View map of stage

Public Rights of Way
Reference
Update
9T/14T
No current closures.
11T
No current closures.
Bridleway number 4T
No current closures.
12T
No current closures.

Stage 3 - Woodmancote and A281

View map of stage

Public Rights of Way
Reference
Update
Footpath 2534
No current closures.
Footpath 2535
No current closures.
Footpath 2540
No current closures.
Footpath 3187
No current closures.
Footpath 3189
No current closures.
Footpath 3188
No current closures.
Bridleway 3672
No current closures.

Stage 4 - Three stream crossings and Horn Lane

View map of stage

Public Rights of Way
Reference
Update
Footpath 2739
No current closures.

Stage 5 - Edburton Road

View map of stage

Public Rights of Way
Reference
Update
Footpath 2739
No current closures.
Footpath 2745
No current closures.
Footpath 2741
No current closures.

Stage 6 - Tottington Mount and South Downs Way

View map of stage

Public Rights of Way
Reference
Update
Bridleway 2754
Long term temporary closure (approx two years). The duration may alter depending on the progress of the works programme. Area is fenced, but PRoW is accessible.
Restricted Byway 2760
No current closures.
Tottington Mount Public Access Land
Long term temporary closure (approx two years) until at least mid 2018. The area is presently fenced off and restricted from access until the reinstatement of the public land has been completed.

Stage 7 - Beeding Hill

View map of stage

Public Rights of Way
Reference
Update
Bridleway 2754
No current closures.
Bridleway 2758
The area is fenced, but the PRoW is accessible and there are no current closures.
Byway 2761
The area is fenced, but the PRoW is accessible and there are no current closures.

Stage 8 - Coombes Road and River Adur HDD

View map of stage

Public Rights of Way
Reference
Update
Footpath 2064/1
The area is fenced, but the PRoW is accessible and there are no current closures.

Stage 9 - Five Ways PRoW Crossing and Titch Hill

View map of stage

Public Rights of Way
Reference
Update
Bridleway 2061/1
The area is fenced, but the PRoW is accessible and there are no current closures.
Restricted Byway No. 2059
The area is fenced, but the PRoW is accessible and there are no current closures.
Bridleway 2075
The area is fenced, but the PRoW is accessible and there are no current closures.

Stage 10 - Lambleys Lane and A27 HDD exit pit

View map of stage

Public Rights of Way
Reference
Update
Footpath 2073
No current closures
Footpath 3134
No current closures
Footpath 3162
The area is fenced, but the PRoW is accessible and there are no current closures.

Stage 11 - Upper Brighton Road to North of Railway

View map of stage

Public Rights of Way
Reference
Update
Footpath 3135
Temporary closure arrangements to allow for vehicle movements across the footpath until approximately mid 2018. The PRoW is accessible.

Stage 12 - North of Railway to Brooklands

View map of stage

30 June 2019
Brooklands – Ongoing works, 3rd – 5th July 2019

Working hours:

Wednesday 3rd July 2019 from 7pm to 9pm

Thursday 4th July 2019 from 5am 7am and 7pm to 10pm

Friday 5th July 2019 from 5am 7am and 7pm to 10pm

These works will involve the delivery of excavation equipment and temporary herras fencing for security of the working area onto the beach on Wednesday 3rd July 2019.

The required works will be concentrated in two areas on the beach in the intertidal zone.

The excavators will be removed from the beach either on Thursday 4th July during the afternoon, or Friday 5th July 2019 afternoon, depending on progress and in line with road space availability.

 

06 June 2019
Brooklands Pleasure Park – Extended working hours, 17th – 19th June 2019

Date and Hours of extended working:

On Monday 17th June 2019 from 7pm to 9pm,

Tuesday 18th June from 5am to 7am and 7pm to 9pm.

Wednesday 19th June 2019 from 5am to 7am and 7pm to 9pm.

The works will involve the delivery of excavation equipment and temporary herras fencing for security of the working area onto the beach in stage 12. Machines will be working on the beach at low tide on Monday 17th and Tuesday 18th.

The machines will then be removed from the beach either on Tuesday or Wednesday evening.